Stoughton 4th Street Dam
Construct additional spillway near existing dam, replacing existing spillway piers, walkway, concrete stability, embankment riprap, and replacement of three slide gates.
CLIENT | City of Stoughton, WI |
DURATION | April 2009 – October 2009 |
SERVICES | Construction Management, Earthwork, Concrete, & Equipment Installation |
COST | $450k |